关于机械竣工? 关于机械竣工,国家建设行业标准中没有明确定义,原因是机械竣工是一种基于合同的标准用语,它的定义在合同中给予明确和定义,宜采用详细的实质内容列举以说明。国外以行业协会和工程公司标准为常见。 现摘录一bn标准。本人英语水平有限,怕对原文意思有曲解,因此采用原文。 mechanical completion when referring to the plant, unit, or facility means that contractor has: provided erection in accordance with drawings, specifications, vendor instructions, applicable codes and regulations and authority requirements. completed all inspection, checking and testing work as listed in the checklist for mechanical completion, applicable to the specific project. it is recognized that painting, paving, insulation, final clean up and removal of temporary facilities must be completed by contractor before plant completion is achieved. however, at the time of mechanical completion of a unit, a system or an area, this work need not be totally complete, but should be in a sufficiently advanced state of completion as not to interfere with subsequent activities. the exceptions as stated above should be included in the punchlist attached to the certificate of mechanical completion. 另外大家可以在fidic条款中查找试试看,我认为也应该有“机械竣工”的定义。查看更多