有国外项目,不敢接手? 第一,明确你承担项目工作内容,搜集所有有关的项目文件和技术资料,把里面的专业词汇挑出来查字典(如果有翻译好的或者原来英文的招标文件等等直接阅读就更好了); 第二,上网,熟悉该国的概况、人文历史等等,掌握基本的礼仪,消除沟通障碍; 第三,除专业词汇以外,掌握英文电子邮件和电话的基本格式、常用语,可以让人觉得你英语需要polish,但不要让人觉得你不懂基本的电邮和电话礼节; 第四,多朗读、多看、多问,别不懂装懂,只有一开始基础好了,后面事情才能理顺! just my two cents! believe in yourself and good luck!!查看更多
turnkey总承包是不是就是EPC总包? • mechanical completion shall have been achieved when all construction activities, installation work, static (non-functional) testing have been completed and documented in accordance with the contract documents. at this point, the turnover system or the facility, as applicable, will be ready to start precommissioning activities. 从以上定义可以看出,机械竣工甚至还不包含单机调试,如果机械竣工就算交接,epc就算完事,实在不可理解啊。实际上,我*司经常要求联机调试甚至投料调试后,才让epc离场的。查看更多