turnkey总承包是不是就是EPC总包? completion of performance test shall include the following: 性能考核结束包括以下: 1 substantial completion has occurred. 实体竣工已经达到 2 commissioning and startup activities are complete. 试车和开车工作已经完成 3 the facility has successfully completed all tests, including performance tests, and shall have achieved the performance guarantee. 装置已经成功完成了所有测试,包括性能考核,并达到性能保证值 4 all items on the punch list have been completed. 所有尾项已经完成 5 the contractor has removed all of its temporary facilities, equipment, materials, tools and personnel from the site. 承包商已将其全部临设、设备、材料、工具和人员从现场移走。查看更多