关于EPC 中三个部分界限划分问题? 国内某些新成立(特别是电力行业)的epc业务公司,感觉主要工作内容包括 设计 采购技术服务 采购 施工管理 调试等内容,究竟e p c的界限怎么划分,有一些误解,我也想寻找一个具体定义,希望有网友能帮忙 以下内容是我看到某外国公司给国内某化工项目做的对epc划分的范例,希望能给大家一点启发: 设计、采购、施工的工作构成 composite epc 基于价格表的构成采用人工时或价格来确定设计、采购、施工三个部分 a composite value of engineering, procurement and construction progress will be calculated by using weighting factors for each of the three components utilizing man-hours or dollars on the basis of the components of the price table. • 设计定义为:包括在 81000系列费用代码下的所有本部办公室工作。包括 工程 设计、采购服务、合同构成和支持工作,如文档控制和项目管理。 engineering is defined as including all home office activities as defined in the 81000 series cost codes. this includes engineering, design, purchasing, contract formation, and support such as document control, and project management. • 采购定义为:包括所有的永久设备和材料费用。这类 费用不包括采购服务,该 费用包含在设计和施工中。 procurement is defined as including all permanent equipment and materials cost. this category excludes the cost of procurement services, which are included in engineering and construction. • 施工定义为: 包括所有施工,施工管理作业施工设备。 construction is defined as including all construction , construction management activities and construction equipment. 80000 lot lot 设计采购及其他服务 费 engineering, procurement and other service eo 81100 mh mh 总体设计及基础设计 费 general design and basic design e 81200 mh mh 详细设计及非标设计 费 detail design and no-standard equipment design e 81300 lot lot 竣工资料费 as-built document e 81400 lot lot 图纸资料翻译复制费 translation and drawing reproduction e 81500 mh mh 采购服务费 procurement service e 查看更多