turnkey总承包是不是就是EPC总包? 回复 4# 智者明 HANDOVER PROCEDURE Mechanical Completion and Pre-Commissioning Tests 1. SCOPE This document prescribes procedure for hand over at time of Mechanical Completion and division of responsibilities between the Owner and the Contractor for the activities involved in the hand over of the Plant, or any portion thereof, constructed by the Contractor in accordance with the Contract. 这是我*司的机械竣工文件,机械竣工和单机调试在一起的,也就是说,机械竣工属于中间交接,只是装置的保管权,使用权,管理权移交给甲方,但这不解除施工单位对工程质量/交工验收应付的责任,如还有质量问题,施工单位仍需负责。EPC也是这么要求,和turnkey是一样的啊。 中间交接的目的只是为了解决施工单位尚未将工程整体移交之前,建设单位有权对部分工程进行试运行作业,例如联动试车。查看更多11个回答 . 2人已关注